Note 16 Other provisions

€ million

Other provisions

Carrying amount as at 1 January 2023

13

   

Movements 2023

 

Added

6

Utilised

-7

Released

-1

Reclassification liabilities held for sale

-

Total

-2

   

Carrying amount as at 31 December 2023

11

   

Movements 2024

 

Added

21

Utilised

-1

Released

1

Reclassification liabilities held for sale

-2

Total

19

   

Carrying amount as at 31 December 2024

30

The other provisions as at year-end 2024 amounted to €30 million (2023: €11 million). 

Other provisions at year-end 2024 include a provision of €20 million for gas connection removals. This provision concerns the costs of removing gas connections where, at the end of 2024, the customer had requested a removal without giving a specific date. If the customer states a specific removal date (preferred date) in the request, the costs of removal are borne directly by the customer. This is also in accordance with the safety route that entered into force on 1 February 2024. No provision is made for future removal requests.

The reclassification to liabilities held for sale relates to the provision for a onerous contract at Warmtenetwerk Hengelo.